November 29 2021
Nove,ber 23 2021
Pouring floor for Paradise 1 model
Adding fill to level the site for the first three new models
November 20 2021
Paradise 3 model waiting for floor pour
November 21 2021
November 22 2021
Paradise 1 model ready for water and electric conduit
December 1 2021
Laying blocks on both models
December 9, 2021
Outside walls almost done
December 10, 2021
pouting floor for paradise 4 model
December 11, 2021
Preparing for roof
December 16, 2021
December 22, 2021
Roof preparation for pouring completed
Pouring roof on Paradise 3 model
December 23, 2021
tapped into the main water line and installed manhole outside of project
Christmas Eve, 2021
Styrofoam roof panels being installed on rare rainy morning in Puerto Peñasco
December 28, 2021
Laying the main water lines into the project
December 29, 2021
Pouring roof on Paradise 1 model
1-3-22
Finishing parapet blockwork
1-6-22
Back wall of project footing and pools dug
1-10-22
Back wall of project footing and pools dug (drone)
Front facade work
1-12-22
Back wall progress
1-17-22
Exterior stucco and interior floor tile in progress on Paradise 3 model
Jan 20, 2022
Front blockwork completed
Prepairing to level the next two lots
1-25-22
Ready to pour carport roof
1-25-22
1-25-22
1-25-22
Prepairing to level the next two lots
Back wall Progress
Casita 3 Cement/sand coated
1-26-22
Digging out pool and finishing back wall
1-25-22
Casita 3 cement/sand coated
1-26-22
Footers laid out for lot 9
1-14-22
Preparing for the carport roof pour
Jan 24, 2022
Prepairing to level the next two lots
Footer and floor pour Lots 9 & 10 - Click to view full screen